Press Release: October 2016 - ITIC warns that failure to follow lay-up procedure can be costly

International Transport Intermediaries Club (ITIC) has reported a case in which a lay-up manager was held liable for a $250,000 contribution to a claim for extensive damage to a vessel whilst in lay-up.

The lay-up manager, as agent for the owner, arranged for a contractor to fit internal blanks to the sea valves of a vessel going into cold lay-up. Subsequently, the vessel's main engine flooded after the valve to the main cooling seawater line was accidentally opened, resulting in serious damage to the machinery and electrics. 

The damage survey found that the internal blanks had not been fitted properly by the contractor, and the owner claimed against the contractor for about $3m. Amid concern that the contractor would not be able to meet such a claim, the owner turned its attention to the lay-up manager, alleging that good practice dictated that all sea valves were to be fitted with internal blank flanges. It added that external sea suctions should have been closed off by divers using fibreglass blanks fitted with neoprene seals. 

The lay-up manager had not arranged for the external suctions to be blanked, and the owner argued that, had the manager arranged for the external blanks to be fitted, there would not have been any flooding. Although the contractor had clearly failed to do its job properly and was primarily liable for the claim, the lay-up manager was required to contribute $250,000 to the overall settlement, which was reimbursed under its ITIC cover.

ITIC says the case also illustrates how the outcome of claims can depend on the way in which a manager contracts. In this case, the manager had appointed the contractor as agent on behalf of the owner, whose claim lay directly against the contractor. If the manager had agreed to provide the blanking on a lump-sum basis, however, the outcome could have been very different, and the manager would have been liable for the actions of the contractor and left to pursue the contractor in a recovery action.

ITIC Press Release PR0816

For more information:  Issued by:
Charlotte KirkChris Hewer
ITICMerlin Corporate Communications
Tel: +44 (0)20 7338 0150Tel: +44 (0)1903 50 20 50
Fax: +44 (0)20 7338 0151Fax: +44 (0)1903 50 02 72
itic@thomasmiller.comchris@merlinco.com
You are currently offline. Some pages or content may fail to load.